Case: “new production line”

New production line

STARTING SITUATION:

The required containers could not be purchased. So, it was decided to make these themselves. Condition: within 3 months, 400 complete sets (consisting of 5 containers) must be ready to deliver. There was nothing yet, except product drawings

CHOSEN APPROACH:

All known data was worked out pragmatically. Takt-time was specified. A first layout was set up with post-its, using the technical drawings. Then the details were worked out further, so the necessary space became